Plant distribution rebuild — Grand Rapids
Scope: Replacement of two 1970s-era 2000A distribution sections, new dry-type transformer, 480V feeders to six production cells, updated arc-flash labeling.
Constraint: Zero production downtime permitted on weekdays. Work executed across three consecutive weekend shutdowns with temporary feeds staged in advance.
Result: Energized on schedule, no lost production hours, full coordination study and as-builts delivered at closeout.